Page 13 - CCGA Best Practices Version English
P. 13

contractor both know the quality of the information included on the plans.
          The facilities shown should include active, abandoned, not-in-use, future
          use, and proposed facilities. The design plans should include a summary
          showing the proposed facility route or excavation. The design plans should
          be provided to affected facility owners in order to provide an opportunity for
          final comment/clarification. Benefits: Providing complete underground facility
          information and including this information on design drawings reduces safety
          hazards, simplifies coordination, and minimizes final project costs.

          Benefits: Providing complete underground facility information and including
          this information on design drawings reduces safety hazards, simplifies
          coordination, and minimizes final project costs.

          Current Practice:
          A potential practice is described below:

          At 30% Design Review
          A utility coordination meeting is set up for the Project Manager to meet with
          all utilities having facilities within the boundaries of the project, as well as
          potential utilities that may wish to place facilities within the limits of the
          project. Plan design drawings and cross sections are circulated to the utility
          companies prior to the meeting highlighting potential conflicts. During the
          meeting the following issues are addressed:
          q  Ensure that all utilities have been correctly identified on the base
            drawings
          q  Identify Areas of conflict
          q  Discuss Potential Solutions
          q  Discuss the Region’s project timing
          q  Address relocation restrictions such as property acquisition, stream or
            railway crossings
          q  Discuss additional test pitting that may be required as well as level of
            detail required (i.e. SUE)
          Minutes should be prepared by the project Manager or his/her consultant and
          circulated to all attendees for verification
          At 60% Design Review
          At the second utility coordination meeting, the utility companies should be
          bringing to the table a drawing (supplied originally by the Region) showing
          how each utility will be addressing their relocates. Each facility’s location
          should be based on Regional standard offsets and comments made at first
          meeting. This meeting should accomplish the following:
          q  Approval in principle is given for the overall co-ordination plan
          q  General timing required for relocation
          q  Date confirmed for receipt by Region for final drawings for approval
            andMunicipal consent
          q  Project timing update
          q  General estimate




                       Canadian Common Ground Alliance
                      Best Practices Version 3.0 – October 2018
          10
   8   9   10   11   12   13   14   15   16   17   18