Page 14 - CCGA Best Practices Version English
P. 14

Minutes should be prepared by the project Manager or his/her consultant and
          circulated to all attendees.
          At 90% Design Review
          By this point in time, the utility relocation plans have been submitted
          and approved, cost sharing estimates (in accordance with the governing
          agreements) have been submitted and approved, written notification to each
          utility mandating relocation (in accordance with the governing agreements)
          has been given and notification time has passed. All land acquisition has
          been secured by the Region, and all utilities should be on site relocating their
          facilities.
          If the utility can only move during the reconstruction contract, a relocation
          timing window must be established to co-ordinate works and provide for a
          separation of time and distance between contractors.

          At Pre-Tender Meeting
          Calls are made to each utility confirming progress on site and ensuring
          relocation complete prior to Region’s contractor on site.
          References:
          •  CSA S250-11, Mapping of Underground Utility Infrastructure




          DESIGN PROCESS




          1-7:  Utility Coordination

          Practice Statement: Project owners and facility owners should regularly
          communicate and coordinate with each other concerning current and future
          projects. Consideration should be given to the establishment of Utility
          Coordinating Committees (UCCs) mandated to deal with specific projects as
          well as issues of concern.

          Practice Description: Project Owners should circulate design drawings to
          facility owners for the purpose of allowing the facility Owner to identify the
          location of their infrastructure, and potential conflicts. The design drawings
          should contain sufficient information of the proposed work to allow the
          facility owner to understand the scope of the work and the impact of such
          work on their structures. Where relocation of facilities will be required,
          a realistic schedule should be developed that allows time for the design,
          construction and budget approval of the relocated facilities.

          Utility coordinating committees provide a mechanism through which winwin
          solutions can be developed for problems associated with the management
          of the public and private infrastructure projects within the public road
          allowance. These problems are generally due to poor communication and


                       Canadian Common Ground Alliance
                      Best Practices Version 3.0 – October 2018
                                                                     11
   9   10   11   12   13   14   15   16   17   18   19