1-18: Demolition Permit Application Process
Practice statement: The Municipality shall have a process requesting that
the demolition permit applicant receives confirmation of all utility disconnects
prior to issuing the demolition permit.
Practice Description: The Municipality shall request that the applicant
makes arrangements with the appropriate utilities for the termination and
capping of all the water, sewer, gas, electric, telephone, cable or other
facilities/services. Furthermore, the Municipality should indicate on the
demolition permit that locates should be obtained from utilities prior to the
demolition beginning.